Check EDMS migration scope, counts, record identities, history, permissions and cutover evidence. Includes a manifest and worked missing-attachment and unknown-access cases.

Assyro Team
10 min read

An EDMS migration passes when the agreed records, context and access work in the accepted destination, with every required exception resolved or formally dispositioned under the approved plan. A successful import job or matching file total is only part of that evidence.

Use this checklist before approving a migration wave or final cutover. It covers record acceptance rather than the full implementation project or a specific export tool. Assyro checked the primary sources on October 6, 2026. The sample below is a documentary exercise, not a completed migration between commercial products.

Set the scope and result rules

Record the source and target systems, configurations, migration wave, extraction cutoff and record owner. Define what moves into the active target, what remains in an accepted archive and what is excluded with justification. Identify the applicable record requirements and intended use.

For every checklist row, retain result, evidence location, owner and decision date. Use these meanings:

  • Pass: the applicable acceptance criterion has supporting evidence for this wave.
  • Fail: observed evidence contradicts the criterion; correction and retest are required.
  • Unknown: evidence, scope or ownership is missing; the row has not passed.
  • Not applicable: a documented reason and authorized reviewer establish that the check does not apply.

A blank is unknown. Mandatory failed or unknown rows prevent cutover. Repeat checks by field, record family or role when their results differ; do not hide a failed subset inside an overall pass. An exception cannot waive an applicable legal obligation; the record owner and designated quality or system approver must accept any permitted alternative against the approved requirements.

Checklist A: define the population before extraction

Comparison table with columns Check, Acceptance evidence, Owner / timing
CheckAcceptance evidenceOwner / timing
Identify each record familyApproved scope names document types and relevant sites/projectsRecord owner / before extraction
Define the counting unitsLogical documents, versions, attachments, renditions and history exports counted separately where presentMigration lead / before baseline
State the retained historyPlan identifies revisions and associated context required in the target or archiveRecord owner / before mapping
Resolve exclusionsEvery excluded population has a reason, destination or authorized dispositionRecord owner / before baseline
Fix the source cutoffTimestamp with time zone and a reproducible inventory query or export specificationSource owner / each wave
Identify active workDrafts, pending approvals and concurrent edits have an explicit handling planProcess owner / before extraction

For EU GMP computerized systems within its scope, Annex 11 section 4.8 calls for migration checks addressing preservation of data value and meaning. The Commission's current index lists the January 2011 revision. That supports evaluating record context, not just whether a file opens. EudraLex index, Annex 11, revision 1.

These checklist rows are proposed acceptance controls, not a universal statutory package. Decide the extent of verification from the actual record risks and intended use. Explain the basis for sampling where used; a successful sample does not excuse a known missing required record.

Checklist B: preserve identity, meaning and history

Comparison table with columns Check, Acceptance evidence, Owner / timing
CheckAcceptance evidenceOwner / timing
Map stable identitiesEach source record/version has a unique target or archive referenceMigration lead / trial and final runs
Reconcile required objectsExpected and observed identity sets match after justified dispositionsMigration lead / each run
Verify metadata meaningRepresentative values retain their meaning, including units, dates and controlled termsRecord owner / mapping test
Verify lifecycle mappingEach source state maps to a defined target behavior; a draft cannot become usable as approvedProcess owner / trial run
Verify historical retrievalRequired prior versions and context can be retrieved through the agreed routeRecord owner / acceptance
Verify signature relationshipsApplicable signature evidence remains connected to the correct record and meaningQuality reviewer / acceptance
Verify audit-history accessRequired change history is readable and attributable through the agreed destinationQuality reviewer / acceptance
Verify links and attachmentsRequired relationships resolve to the correct version or objectTechnical reviewer / each run

Do not infer equivalence from similar labels. A source “approved” state may mean signed but not effective, while the target's similarly named state permits use. Write the mapping in terms of behavior and test the affected access or workflow.

A hash comparison can support a byte-integrity check for an unchanged file. It does not prove the correct source was selected, the metadata is meaningful or the target permission is appropriate. A planned format conversion may change the bytes and needs its own acceptance method.

Where Part 11 applies to a closed system, 21 CFR 11.10 includes controls for copies, retrieval, access and audit trails. Evaluate those requirements with FDA's scope and application guidance and the relevant underlying record rules; do not assume every file has the same obligations. 21 CFR 11.10, FDA Part 11 guidance.

Checklist C: test access and reconcile exceptions

Comparison table with columns Check, Acceptance evidence, Owner / timing
CheckAcceptance evidenceOwner / timing
Test permitted accessRepresentative authorized users can retrieve the scoped records and contextAccess owner / trial and cutover
Test denied accessAn unauthorized role cannot open, change or approve the tested record as applicableAccess owner / trial and cutover
Check identity mappingHistorical actors remain distinguishable, including departed usersRecord owner / mapping test
Capture every discrepancyException register links the affected object, failed criterion and evidenceMigration lead / each run
Verify corrected objectsRetest result refers to the corrected run and exact objectAssigned reviewer / before closure
Approve alternative retentionAny archive substitute meets the stated retrieval and preservation requirementsRecord owner and quality / before cutover

An administrator's successful search is not an access test for ordinary users. Test a restricted reader and an unauthorized role separately. Also distinguish the original historical author from the account that performed the import; rewriting every past action as the migration account destroys that distinction.

An accepted archive can be part of the design, but it must be a usable, governed destination. Identify its access route, owner, retrieval method and required availability. “Keep the old server somewhere” does not resolve an untested retention dependency.

Use this migration manifest

Keep one row per counted object, with relationships back to its logical document. Record the run ID and scope baseline in the manifest header. The table is a suggested working schema; adapt it without losing the ability to reconcile exact objects.

Comparison table with columns Manifest field, Required meaning
Manifest fieldRequired meaning
Source namespace and logical IDIdentifies the source system/organization and document without collisions
Object type and object IDDistinguishes version, attachment, rendition or history package
Source revision and stateCaptures the expected version and lifecycle meaning at cutoff
Parent / relationshipLinks the object to its document and, where relevant, exact version
Target or archive referenceNames the accepted destination object and mapped state
Transformation referenceIdentifies the approved conversion or metadata mapping, if used
Verification evidenceRecords identity, content/context and relationship check results
Disposition / exceptionPass, fail, unknown or justified exclusion, with owner and closure evidence

Use stable IDs as the reconciliation key. Filenames and titles can help a reviewer but may be duplicated or changed. Keep authoritative metadata in the controlled source or accepted target; the manifest should reference it rather than create a competing editable master.

Worked example: matching totals can still hide loss

Consider a fictional four-document migration wave. The agreed version inventory is D10/v1–v2, D20/v1–v3, D30/v1 and D40/v1–v2: eight version objects. It also contains three attachments, A1, A2 and A3, and four separately counted history packages. A3 belongs to D40/v2.

Comparison table with columns Counting unit, Expected, First target result, Decision
Counting unitExpectedFirst target resultDecision
Logical documents44Count matches; identity checks still required
Version objects88Count matches; revision/state checks still required
Attachment objects32Fail: A3 absent
History packages44Count matches; contents and retrieval still require review

Do not add these figures into one ambiguous “document count.” They represent different units and relationships.

The migration lead reruns the attachment import. It now reports three successful rows, but the observed IDs are A1, A2 and A2. The total matches while A3 is still missing and A2 is duplicated. The attachment check remains failed.

After correction, the target contains A1, A2 and A3, and A3 opens from the correct D40/v2 relationship. That resolves the attachment exception. It does not automatically close the other checklist rows.

Populate the decision log as follows:

Comparison table with columns Condition, Evidence location, Result, Action / owner
ConditionEvidence locationResultAction / owner
A3 present and linked to D40/v2 after correctionCorrected manifest M03 and link-test record T07PassReviewer closes attachment exception E04
A3 absent in the first runManifest M01 comparisonFail for that runMigration lead corrects and submits retest
Unauthorized-role test for D40 lacks evidenceAccess-test register, required row blankUnknownAccess owner executes and records the test before cutover
Rendition-object migrationApproved source inventory records no rendition objects in this scopeNot applicableRecord owner records the scope-based reason

The wave is not ready while the required access test remains unknown. After that test passes and the remaining required checks are accepted, the authorized approver can release this wave. A later success does not erase the failed run's history.

Checklist D: control the delta and cutover

Comparison table with columns Check, Acceptance evidence, Owner / timing
CheckAcceptance evidenceOwner / timing
Establish the final change boundaryFreeze or controlled delta procedure identifies when the source can still changeSource owner / cutover window
Reconcile additions and revisionsChanges since the baseline appear in the final manifestMigration lead / final run
Reconcile removalsDeleted or withdrawn source records have defined final dispositionsProcess owner / final run
Reconcile state changesLifecycle changes since the cutoff produce the intended target behaviorProcess owner / final run
Reconcile access changesPermission changes since the cutoff appear in the accepted access configurationAccess owner / final run
Identify the authoritative systemUsers know which system can accept each record action after cutoverSystem owner / before release
Define rollback conditionsNamed triggers and decision authority are recordedCutover owner / before release
Preserve post-cutover writesRollback or recovery accounts for records created or changed in the targetSystem owner / rehearsal
Accept the retained access routeTarget and any required archive remain retrievable after source access changesRecord owner / before retirement
Authorize source retirementAccepted transfer, retention needs and unresolved dependencies permit the specified retirement actionRecord owner and quality / after acceptance

Rollback is not merely turning the old system back on. If users have created records in the target, define how those records are preserved and reconciled before changing authority again. Rehearse the agreed recovery approach without destructive, unplanned production changes.

Extend the fictional wave: after baseline extraction, D40/v2 is withdrawn and one reader loses access. No document or attachment count changes. A final run that checks counts alone misses both changes. The process owner verifies D40/v2's intended retained-but-withdrawn behavior, and the access owner repeats retrieval with the revoked account. Separately, if D50/v1 was created in the target after cutover, record its owner and recovery destination before any rollback. An unknown destination blocks the proposed rollback decision; switching the old server on cannot prove D50 was preserved.

Once all mandatory checks pass or have an authorized, requirement-satisfying disposition, record the exact accepted wave, manifest revision, exceptions and cutover decision. Keep failed and corrected run evidence accessible. Do not delete the source merely because the import service returned a success message.

For the wider evidence plan, see our computerized system validation guide. For lifecycle and effective-state questions, use the QMS document control guide.

If you are evaluating a regulatory-document handoff involving Assyro, bring a representative manifest and exception to the discussion. Confirm the actual destination capabilities and responsibilities. This checklist can structure that review; completing it does not itself certify a system or establish regulatory acceptance.